Information on the St Aubyn's Development

Latest News
 

The Twitten will close for 5 days from 20 July until 25 July while buildings backing on to it are demolished.  Barriers and notices have been placed at each entrance.

St Aubyn's developers parking on Steyning Road. The Parish Council are aware of recent problems with the Demolition Contracters parking on Steyning Road and have taken up the matter with the site manger. He has apologised and will ensure that future parking on Steyning Rd by the demolition contractors is confined to the 5 allocated spaces as agreed at paragraph of  3.10 of the Demolition Environmental Management Plan.

Demolition Schedule

The developers have just advised that followinng following removal of interior structures, the team will demolish buildings as follows;

  • 8-12 June. Headmaster’s house
  • 15-19 June. Computer block
  • 22-26 June. Design classrooms and science block
  • 29 June-10 July. Toilets, swimming pool and other ancillary buildings.
  • 13 July onwards. The school buildings not to be retained (see demolition map below).
  • Early-mid August demolition to finish.

It is important to note that this is a rough guide only which may change as the work progresses.  For safety reasons, the demolition contractors anticipate that the Twitten will require a temporary closure for one week whilst the structures closest to it are taken down. Thus will probably be towards the middle to end of July. Prior notice will be given once an exact date is set. 

 A map showing the buldings to be demolished is here

The Demolition Phase Agreement 

During the demolition phase of the work Brighton and Hove City Council and Rottingdean Parish Council will be working closely with Fairfax Properties and the demolitionn contractor to ensure that disruption to the villagebis kept to a minimum. This will include regular meetings and site visits

As part of the the planning permission, certain conditions for the demolition have been agreed to manage the local impact.  These cover how noise and dust will be managed, how entry and exit from the site will be arranged, the routing of demolition traffixc through the village and how any road or path closures will be managed. A summary of the agreement is 
here The full agreement is contained in the Demolition Environmental Management Plan

Former St Aubyns School 

St Aubyns Planning Brief passed 15th January 2015 